BL Silver Coat RT is applied in the following three steps.

1Undercoat / Primer Application
30 minutes of forced drying at 80~120 ℃.
In case of drying at room temperature, allow it to dry for 5~7 days or more following application.

2Intermediate / Silver Application
10 minutes of forced drying at 80~120 ℃.
In the case of drying at room temperature, allow it to dry for 48 hours or more following application.

3Overcoat / Clear Topcoat Application
30 minutes of forced drying at 80~120 ℃.
In case of drying at room temperature, allow it to dry for 5~7 days or more following application

Point # 1 : Complete Removal of the Thinner
After each step, it is important to make sure that all traces of the thinner have evaporated and is no longer in the surface. Regardless of using forced drying or drying at room temperature, all of the volatile components of thinner should be removed. If there is still component traces of the thinner, it may impact the development of the silver finish (the color may become affected/turn bluish).
Point #2 : Temperature Settings while using of Forced Drying
Forced drying requires for the temperature to be constant at 80°~120 C. Rather than just the temperature setting of the drying furnace, the temperature of the entire piece being worked on. In addition, after finishing the piece from forced heating, please allow it to return to room temperature before proceeding to the next coating step.
Point #3 : Foundation Building
Since BL Silver Coat works with completely with a very thin film, the base preparation for the application surface is very important. Priming of the application surface and preparing it to be totally smooth for a perfect mirror surface state is recommended.

Procedure Instructions

Primer : Application of Primer

[ Mixing Ratio ] The main agent : curing agent = 6 : 1 ( mass ratio )
[ Dilution Ratio ] base resin : hardener : thinner = 6 : 1 : 40-60% ( mass ratio )
[ Paint Viscosity ] : 8-10 S / IHS
[ Time required for levelling ] : 5-10 minutes / heat treatment, be sure of the course after application at this time.
[ Recommended thickness ] : 10~20μm
[ Drying Times ]
30 minutes at forced drying = 80~120 ℃.
If drying at room temperature ( 25 ℃ as standard ) please let stand for at least 5~7 days after application.
However, outdoor drying time depends on the normal temperature and humidity of the environment and varies by region and/or weather conditions.

Intermediate : Application of Silver

[ Dilution Ratio ] silver : thinner = 1 : 1.6 ( mass ratio )
[ Paint viscosity ] : 6~8 S / IHS
[ Time required for levelling ] : 5-10 minutes / heat treatment, be sure of the course after application at this time.
[ Recommended thickness ] : 0.2μm
[ Drying Times ]
10 minutes at forced drying = 80~120 ℃.
If drying at room temperature ( 25 ℃ as standard ) please let stand for at least 5~7 days after application.
However, outdoor drying time depends on the normal temperature and humidity of the environment and varies by region and/or weather conditions.

【 Important! 】Recommended settings for the spray gun
Side Port Control : Full Open
Fluid Control Knob : 1-1/4″
Air Adjusting Valve : 0,2Mpa
Needle : 1.1mm

Dilution Ratio / silver : thinner = 1 : 1.6

We recommend that silver be applied 3 to 10 times.
As the number of times of silver coating increases, it is possible to obtain richer metallic tone.
Overcoat : Construction of the Clear Topcoat

[ Mixing Ratio ] the main agent : curing agent = 8 : 1 ( mass ratio )
[ Dilution Ratio ] the main agent : hardener : thinner = 8 : 1 : 40-60% (mass ratio )
[ Paint viscosity ] : 8-10 S / IHS:
[ Time required for levelling ] : 5-10 minutes / heat treatment, always passed this time post-construction of that.
[ Recommended thickness ] : 10~20μm
[ Drying Times ]
30 minutes at forced drying = 80~120 ℃.
If drying at room temperature ( 25 ℃ as standard ) please let stand for at least 5~7 days after application.
However, outdoor drying time depends on the normal temperature and humidity of the environment and varies by region and/or weather conditions.
The Clear Topcoat is a urethane-based paint, so it’s possible to add toning pigment.

Movie

 

BL Silver Coat RT

How to Order

Paint in general is treated as hazardous goods, so for shipping charges, we must make individual estimates by airline according to country and region.

First, please send us the order form below. We will calculate the shipping charges to your nearest airport / Term : CIF.
We will then send you a bill including those shipping charges via paypal. After checking that amount, please decide whether or not to purchase our products.
paypal is our only payment method. You can cancel the order at any time.
Furthermore, please note that it will be about 10~14 days before items are shipped.






    Order

    We will then send you a bill including those shipping charges via paypal.

    Name

    E-mail

    Reenter e-mail ( *Required )

    Zip code

    Address

    Country

    Telephone number

    Item

    The number of orders

    Message

    Estimated shipping charges

    Forwarder & Transportation : ANA cargo or K-Line Logistics
    The minimum fee is set for international transportation of dangerous goods.
    The following is the minimum fee in each region.

    North america / Australia / Oceania / Asia : 45,000〜65,000JPY
    Central America : 55,000〜65,000JPY
    South America : 75,000〜85,000JPY
    Europe / Russia : 60,000〜75,000JPY
    India / Middle east : 75,000〜85,000JPY
    Africa : 65,000〜85,000JPY

    Recruiting Distributors & Dealers

    Contact : Recruiting Distributors & Dealers

    BL HY-COATER
    PRESENCE Co., Ltd. / BADLAND
    4-18-1 Minamikase Saiwaiku Kawasaki Kanagawa JAPAN
    ZIP CODE : 212-0055
    TEL +81-44-587-3139 / FAX +81-44-580-3431 / e-mail : info@badland.net


    Leave A Reply

    *
    *
    * (公開されません)

    Comment On Facebook